Five Massive Towers for Machinery in Africa

Introduction: In Africa, we built five massive towers for a German machinery manufacturer, serving as bases for various machine units. These towers had to meet stringent structural requirements while remaining adaptable for different machine configurations.

Challenges: The installation took place in tight halls, requiring complex logistics and specialized lifting methods. Moreover, impeccable dimensional accuracy was necessary so that machines could be mounted precisely later on.

Solution: We produced the steel framework in the form of modular tower segments, which were then assembled on site with millimeter precision. Thorough pre-planning and close coordination with the machinery manufacturer enabled a delay-free completion.

Result: The five towers stand firmly and provide sufficient load capacity for the subsequent machine installations. The client benefited from a smooth industrial construction process and a highly accurate steel construction solution.

Facts (Project 17):

Tonnage Location Project Type Date
300 tons steel Africa Industrial Construction January 2024