Pilot Installation of the New Stacheteystem
Introduction: On the Swabian Alb, we conducted a pilot installation of our new stachetsystem, which features a sleek design and high levels of prefabrication. Intended for residential projects, this system was set up in a very short timeframe.
Challenges: As this was a newly developed system, all components had to be perfectly coordinated and installed within just two days. Additionally, the double-rod post design was required to ensure a modern look without sacrificing durability.
Solution: We industrially prefabricated all modules and delivered them as a modular system to the site. Thanks to precise plug-and-bolt connections, 90 linear meters of fencing were installed on schedule, demonstrating the system’s efficiency.
Result: The client gained a stylish, long-lasting enclosure that blends seamlessly with the residential environment. For us, this project serves as a successful reference, already leading to the next order of 150 balconies using the same system.
Facts (Project 7):
Tonnage | Location | Project Type | Date |
6 tons | Swabian Alb | Residential | January 2025 |